Shed Permit Cost in Arlington, TX (2026)
Shed permit fees for the City of Arlington, Texas (Tarrant County), pulled directly from the Planning and Development Services Fee Schedule, effective October 1, 2025 (Resolution No. 25-258, Exhibit A). Arlington splits accessory buildings by size. A portable storage or accessory building 320 square feet or under is a flat $50.00 building permit – the exact printed line, the same $50.00 as a residential-lot fence – and under our reading of the schedule no plan review line applies to it. A permanent accessory building over 320 square feet (or a detached garage) is priced instead by the city's Table 1 valuation schedule, so its fee scales with the declared value of the work, and Arlington adds a non-refundable 35% plan review on that building permit. The $50.00 does not include wiring; a shed with power adds a separate $100.00 electrical trade permit. Texas has no statewide permit levy and Arlington adds no technology surcharge. This schedule is current (effective October 1, 2025, re-verified October 6, 2026), so the source-age caveat that applies to some Texas cities does not apply here.
This guide covers: The City of Arlington, Texas (Tarrant County) residential shed and accessory-building permit lines as printed in the Planning and Development Services Fee Schedule, Exhibit A. The headline is the flat $50.00 "Portable storage / accessory building 320 square feet or under" line – exact from the published schedule. That $50.00 is the building permit for a typical prefab or portable backyard shed.
The size cutoff is the key rule: the flat $50.00 applies at 320 square feet or under. A permanent accessory building over 320 square feet, or a detached garage, is priced by the city's Table 1 valuation schedule instead, so its fee rises with the declared value of the work. That means a large workshop is not a flat $50.00 – its permit, plus the 35% plan review, could run into the hundreds of dollars depending on valuation.
Trade permits are separate: the $50.00 is the building permit only. If the shed gets electrical, mechanical, or plumbing work, each associated trade permit is a separate flat $100.00 on the Arlington schedule. A wired shed is therefore about $150.00 across the building and electrical permits – a labeled estimate, not one printed line.
Plan review (our reading): Under our reading of the schedule, no plan review line applies to a shed of 320 square feet or under: Arlington adds a non-refundable plan review fee of 35% of the building permit fee on items its schedule marks for plan review (including permanent storage / accessory buildings over 320 square feet and detached garages), and the portable storage / accessory building 320 square feet or under line is not marked; confirm with Arlington Planning and Development Services. A building over 320 square feet adds 35% of its Table 1 building permit fee.
This guide does NOT cover: zoning setback, easement, and Unified Development Code placement rules; homeowners-association approval; concrete slab or foundation work; impact fees; the separate $100.00 trade permits; and any Tarrant County fees. The dollar figures for over-320-square-foot buildings depend on the declared valuation and are examples, not fixed amounts.
A portable storage or accessory shed 320 square feet or under in Arlington, TX is a flat $50.00 building permit under the Planning and Development Services Fee Schedule (Exhibit A, effective October 1, 2025) – the exact printed line, the same $50.00 as a residential-lot fence, with no plan review line under our reading of the schedule. A permanent accessory building over 320 square feet, or a detached garage, is priced by the city's Table 1 valuation schedule plus a 35% plan review instead – for example, a 400-square-foot building at an assumed $30,000 valuation is about $775.58 ($574.50 building permit + $201.08 plan review). The $50.00 does not include power; wiring the shed adds a separate $100.00 electrical trade permit, making a small wired shed about $150.00. Texas adds no state levy and Arlington adds no technology surcharge.
- Arlington, Texas charges a flat $50.00 building permit for a "portable storage / accessory building 320 square feet or under" on the Planning and Development Services Fee Schedule (Exhibit A). That $50.00 is the exact printed figure for a typical prefab backyard shed.
- The 320-square-foot cutoff controls the price. A permanent accessory building over 320 square feet, or a detached garage, is priced by the Table 1 valuation schedule, so its permit scales with the declared value of the work (plus a 35% plan review) rather than staying at $50.00.
- Trade permits are separate. Electrical, mechanical, or plumbing work on the shed is a flat $100.00 each on the Arlington schedule, so a wired shed is about $150.00 across the building and electrical permits – a labeled estimate, not a single printed line.
- A worked Table 1 example: a 400-square-foot permanent accessory building at an assumed $30,000 valuation is about $574.50 building permit ($532.00 at $25,000 plus $8.50 per $1,000 for the next $5,000), plus a 35% plan review of $201.08, for about $775.58. The exact figure depends on the department's declared valuation.
- Under our reading of the schedule, a shed of 320 square feet or under is not marked for Arlington's 35% plan review, so no plan review line applies; a permanent building over 320 square feet is marked and adds 35% of its building permit fee. Texas has no statewide percentage levy and Arlington adds no technology surcharge.
- The schedule is effective October 1, 2025 (Resolution 25-258) and was re-verified October 6, 2026, so no source-age caution applies. For same-city context, see the Arlington pool permit guide and the Arlington fence permit guide.
Arlington Shed Permit Fee Structure
The shed permit hinges on one number: 320 square feet. At or under that, the building permit is a flat $50.00 with no plan review line under our reading. Over it, the fee moves to the Table 1 valuation schedule, scales with declared value, and adds a 35% plan review. Trade permits are separate. The table below shows the flat line, the valuation path, plan review, and the trade permits, so you can see what is and is not part of the $50.00. Every printed amount is exactly as it appears on the schedule.
| Item | Fee | How It Is Applied |
|---|---|---|
| Portable storage / accessory building ≤320 sq ft | $50.00 flat | Exact printed line on Exhibit A. The building permit for a typical prefab or portable backyard shed at or under 320 square feet. |
| Permanent accessory building >320 sq ft / detached garage | Table 1 valuation | Priced on declared value at an assumed $75.00/sq ft. Table 1 is $325.00 up to $2,000, then $325.00 plus $9.00 per additional $1,000 to $25,000 ($532.00 at $25,000), $8.50 per $1,000 to $50,000 ($744.50 at $50,000), and so on. A 35% plan review is added. |
| Electrical / mechanical / plumbing (each, if added) | $100.00 each | Associated trade permits, separate flat fees added to the building permit. Not bundled into the $50.00. |
| Plan review (35% of the building permit fee) | None ≤320 sq ft; 35% above | Non-refundable, assessed at submittal on items the schedule marks for plan review. On our reading the ≤320 sq ft portable/accessory line is not marked (no plan review), while a permanent building over 320 sq ft is - confirm with the city. |
| Fence residential lot (context) | $50.00 | Sibling flat line at the same $50.00 as a portable shed. Shown for context, not added. |
| State / city percentage levy | None | Texas has no statewide permit levy and Arlington adds no technology surcharge to the shed line. |
Source: City of Arlington (TX) Planning and Development Services Fee Schedule, effective October 1, 2025 (Resolution No. 25-258, Exhibit A). The $50.00 portable/accessory-building ≤320 sq ft line, the Table 1 valuation schedule for larger permanent buildings, the $100.00 per-trade permit fees, and the 35% single- and two-family plan review fee all appear on the city schedule. Under our reading of the schedule, no plan review line applies to a shed of 320 square feet or under: Arlington adds a non-refundable plan review fee of 35% of the building permit fee on items its schedule marks for plan review (including permanent storage / accessory buildings over 320 square feet and detached garages), and the portable storage / accessory building 320 square feet or under line is not marked; confirm with Arlington Planning and Development Services. The over-320-square-foot figures depend on declared valuation – confirm the current amount and how your structure is classified with Development Services.
Worked Examples - Real Shed Projects in Arlington
For a typical backyard shed, the building permit is a flat $50.00. What raises the cost is crossing 320 square feet into the valuation schedule, or adding power. Each example below separates the exact printed line from any labeled estimate.
A homeowner sets a 10 ft x 20 ft (200 sq ft) prefab storage shed on a gravel pad, no electrical.
- Portable / accessory building ≤320 sq ft: $50.00
- Trade permits: not added (no wiring)
- City plan review: none (line not marked, our reading)
- Total: $50.00
The $50.00 is the exact printed flat line at or under 320 square feet. Setback and placement rules still apply, but they carry no fee on this line.
The same 200 sq ft shed, but the owner runs a circuit from the house for lighting and one outlet.
- Portable / accessory building ≤320 sq ft: $50.00
- Electrical trade permit: $100.00
- Estimate: $150.00
The $50.00 building line and the $100.00 electrical trade permit are both exact printed lines; the $150.00 combined figure is a labeled estimate across two separate permits.
A homeowner builds a 400 sq ft permanent, foundation-set workshop – over 320 square feet, so it is priced by Table 1 at an assumed $75.00/sq ft valuation ($30,000).
- Assumed valuation: 400 × $75.00 = $30,000
- Table 1: $532.00 at $25,000 + $8.50 × 5 = $574.50
- Plan review: 35% × $574.50 = $201.08
- Trade permits, if wired: $100.00 each, separate
- Estimate: $775.58 building + plan review (plus trades)
Over 320 square feet, the flat $50.00 does not apply. The $775.58 is a labeled estimate driven by the assumed $30,000 valuation (Table 1 adds the per-$1,000 rate for each additional $1,000 or fraction thereof); the plan review is applied on our reading that permanent buildings over 320 sq ft are marked for plan review, and the department's declared valuation sets the actual figure.
When This Estimate May Not Apply
The flat $50.00 covers a portable storage or accessory building 320 square feet or under. Route your project to Development Services before relying on this figure if any of the following applies:
- Your building is over 320 square feet. A permanent accessory building above 320 square feet, or a detached garage, is priced by Table 1 valuation plus a 35% plan review, not the flat $50.00. The permit scales with declared value and can run into the hundreds.
- You are wiring or plumbing the shed. The $50.00 is the building permit only. Each associated trade permit – electrical, mechanical, plumbing – is a separate flat $100.00.
- The plan review reading changes. We do not apply Arlington's 35% plan review to the ≤320 sq ft line because the schedule does not mark it for plan review. If the department assesses plan review on your shed, it would be 35% of $50.00 ($17.50) - confirm with Development Services.
- Your structure is classified differently. Whether a build is a "portable / accessory building 320 square feet or under" or a valuation-priced permanent building is a department call. Confirm the classification before assuming $50.00.
- Zoning, placement, or HOA rules affect your shed. Unified Development Code setback and placement rules and any homeowners-association approval are separate from the fee and can restrict where or how large a shed may be.
- The schedule has been amended. The fees are effective October 1, 2025 as Phase II of Arlington's 2025 permit-fee adjustments (no later phase announced as of October 6, 2026). Confirm the current amount before budgeting.
Zoning and placement rules, HOA approval, slab or foundation work, impact fees, the separate $100.00 trade permits, and any Tarrant County fees are excluded from the $50.00 shed figure on this page, and the page-standard disclaimer applies. Always verify the current amount and your structure's classification with Arlington Development Services before budgeting.
Arlington Shed Permit Cost vs Other Verified Texas Cities
Texas cities price shed and accessory-building permits differently – some as a single flat fee, some tiered by size, some by valuation. Scope differs, so each figure below notes its basis, and each department should be verified separately.
| City | Shed / Accessory Fee Basis | Typical Backyard Shed Permit |
|---|---|---|
| Arlington, TX | Flat ≤320 sq ft; valuation + 35% plan review above | $50.00 (≤320 sq ft) |
| Carrollton, TX | Flat "Storage shed" specific permit | $50.00 flat |
| Grand Prairie, TX | Tiered by size | $20 / $100 / $0.25 per sq ft |
| New Braunfels, TX | Flat, site-built vs pre-built | $75 / $50 (~$113 all-in) |
Scope note: Arlington charges a flat $50.00 for a portable storage or accessory building 320 square feet or under, moving to Table 1 valuation plus a 35% plan review above that size - the same $50.00 as Carrollton's flat shed permit and New Braunfels' pre-built base. Carrollton charges a flat $50.00 stand-alone "Storage shed" specific permit at any size. Grand Prairie tiers by size ($20.00 up to 100 sq ft, $100.00 for 100–400 sq ft, $0.25 per sq ft above). New Braunfels charges $75.00 site-built or $50.00 pre-built, plus fees. Compare the basis, not just the number, and confirm current figures with each department.
See Arlington's full fee schedule, or price other Arlington projects.
Frequently Asked Questions
Who to Contact
| Department | City of Arlington, Texas - Planning and Development Services |
| County | Tarrant County, Texas |
| Permit portal | Arlington Online Permits (ap.arlingtontx.gov) |
| Ask them | Whether your shed is a flat $50.00 portable/accessory building or a Table 1 permanent building, whether a $100.00 trade permit is needed, whether the 35% plan review applies, and whether the schedule has changed |
| Fee schedule | Arlington Planning and Development Services Fee Schedule (effective Oct 1, 2025) |
Sources
-
City of Arlington, TX - Planning and Development Services Fee Schedule (effective October 1, 2025) Arlington, TX (Tarrant County) - official Planning and Development Services Fee Schedule, Resolution No. 25-258, Exhibit A. Primary source for the $50.00 portable/accessory-building ≤320 sq ft line, the Table 1 valuation schedule for larger permanent buildings, the 35% single- and two-family plan review fee, and the $100.00 per-trade permit fees. Effective October 1, 2025; re-verified October 6, 2026.
-
Texas Local Government Code, Chapter 214 Texas statute (.gov) confirming municipal building-regulation authority and that Texas imposes no statewide percentage building-permit levy. Context for the "no statewide levy" statement. Verified August 2026.