Howard County vs Baltimore County, MD Building Permit Fees (2026)

Howard County and Baltimore County are neighbors with very different fee mechanics. Howard meters square footage - $0.25 per square foot for additions, plus a $50 filing fee and a 10% technology fee. Baltimore County charges flat fees by size band - an addition is $105 under 600 square feet ($160 with structural changes) and $160 at 600 square feet and over, plus a separately listed $75 application fee and no technology fee. On larger additions Baltimore County is cheaper either way; on smaller ones the lower county depends on whether Baltimore County credits its $75 application fee toward the permit. Baltimore County's schedule took effect July 1, 2026.

Key Takeaways
  • Howard prices additions per square foot ($0.25/sq ft + $50 filing + 10% technology fee); Baltimore County charges flat by size band ($105 under 600 sq ft, $160 at 600 sq ft and over or with structural changes) plus a $75 application fee.
  • A 400 sq ft addition: about $160 in Howard vs $105 to $180 in Baltimore County ($160 to $235 there with structural changes) - which is lower depends on whether Baltimore credits its $75 application fee.
  • An 800 sq ft addition: about $270 in Howard vs $160 to $235 in Baltimore County, so Baltimore is $35 to $110 lower.
  • Baltimore County's flat-by-size-band fees are cheaper for larger additions (about 673 sq ft and over, whether or not the $75 is credited) because they do not scale with each square foot and carry no technology fee.
  • New construction is not directly comparable: Howard charges $0.25/sq ft (about $810 for a 2,400 sq ft house), while Baltimore County lists a Category D minimum of $280 with no residential per-square-foot rate published.
  • Neither county adds a statewide Maryland levy. Howard's schedule is current (July 1, 2026), and so is Baltimore County's (July 1, 2026). Baltimore County's $75 application fee is shown both ways because its schedule does not say whether it is credited.

Howard vs Baltimore County: Fee Structure Side by Side

Fee Element Howard County (DILP) Baltimore County (PAI)
Addition $0.25 / sq ft + $50 filing $105 (<600 sq ft) / $160 (600+ or structural)
Deck Priced per sq ft (no separate deck line) $105 (<600 sq ft) / $150 (600+)
New 1-2 family dwelling $0.25 / sq ft (+ $100 filing) Category D, $280 minimum + $50 guaranty fund (per-sq-ft rate unpublished)
Residential solar Electrical trade permit (separate) Flat $100
Fence Confirm with DILP Flat $35 (residential)
Technology fee 10% of permit fee None
State levy None (Maryland) None (Maryland)
Fee schedule effective July 1, 2026 (FY2027) July 1, 2026

Baltimore County's flat-by-size-band model means a 200 sq ft and a 590 sq ft addition pay the same $105 (without structural changes); Howard's per-square-foot model charges more as the addition grows. Baltimore County also lists a $75 residential application fee on all permits. Baltimore County's schedule lists a separate $75 residential permit application fee and does not say whether it is credited toward the permit fee, so PermitPrice shows Baltimore totals with and without it and will update them once the county confirms.

Shared-Assumption Worked Examples

Each example assumes the same addition size for both counties. Trade permits are excluded on both sides.

Example 1: Room Addition - 400 sq ft

Fee Component Howard County Baltimore County
Building permit fee 400 × $0.25 = $100.00 Flat $105.00 (<600 sq ft)
Filing / application fee $50.00 $0.00-$75.00 (may be credited)
Technology fee (10%) $10.00 $0.00
Total $160.00 $105.00-$180.00

Note: No winner can be stated for this example yet. Howard's $160 is $20 below Baltimore County's $180 if the $75 application fee is additional, but $55 above Baltimore County's $105 if the fee is credited toward the permit. With structural changes, Baltimore County's under-600 sq ft fee is $160 ($160 to $235 total): a tie with Howard if credited, $75 more if not.

Example 2: Larger Addition - 800 sq ft

Fee Component Howard County Baltimore County
Building permit fee 800 × $0.25 = $200.00 Flat $160.00 (600 sq ft and over)
Filing / application fee $50.00 $0.00-$75.00 (may be credited)
Technology fee (10%) $20.00 $0.00
Total $270.00 $160.00-$235.00

Note: Baltimore County's $160 to $235 ($160 flat fee for 600 sq ft and over, plus $75 if the application fee is not credited) is $35 to $110 under Howard's per-square-foot total, and the gap widens as the addition grows.

New Construction - Not Directly Comparable

A new 2,400 sq ft house is about $810 in Howard County ($600 permit at $0.25/sq ft + $60 technology fee + $100 filing + $50 guaranty). Baltimore County lists residential new construction under Fee Category D with a $280 stated minimum (plus a $50 MD Home Builders Guaranty Fund and the $75 application fee), but no per-square-foot residential rate is published on the fee schedule, so a true head-to-head total cannot be computed. We do not publish a single Baltimore County new-home figure here. Both counties also assess large separate impact and school charges on new homes, excluded throughout.

Which County Is Cheaper for Your Project?

Scenario Lower Fee Why
Addition under 600 sq ft Howard under 200 sq ft; Baltimore from about 473 to 599 sq ft; depends on the $75 credit in between ($160 vs $105-$180 at 400 sq ft) If the $75 is additional, Howard stays below Baltimore's $180 until about 473 sq ft; if it is credited, Baltimore's $105 is lower from 200 sq ft up (a tie at 200). With structural changes Baltimore is $160-$235
Addition 600 sq ft and over Baltimore from about 673 sq ft either way ($160-$235 vs $270 at 800 sq ft) Baltimore's $160 (plus $75 if not credited) stays fixed; Howard keeps charging per sq ft. From 600 to about 672 sq ft Howard is lower only if the $75 is additional
New 1-2 family dwelling Not directly comparable Baltimore's residential per-sq-ft rate is unpublished
Confidence / currency Both current Howard FY2027 and Baltimore County both took effect July 1, 2026
Solar / fence Baltimore lists flat fees ($100 / $35 building permit, plus a $75 application fee that may be credited) Howard routes solar through a separate electrical permit

On additions, Howard is lower under 200 sq ft and Baltimore County is lower from about 473 to 599 sq ft and from about 673 sq ft up, whether or not its $75 application fee is credited; at other sizes the winner depends on that credit, because Baltimore's flat fees ignore square footage while the $75 fee, if additional, raises the floor. Both schedules took effect July 1, 2026.

Practitioner Insight

For additions, the winner depends on size. Baltimore County's July 1, 2026 schedule charges $105 under 600 square feet ($160 with structural changes) and $160 at 600 and over, plus a separately listed $75 application fee. Howard's $0.25 per square foot plus a $50 filing fee and a 10% technology fee comes to about $160 on a 400 sq ft addition against Baltimore County's $105 to $180, so the small-addition winner depends on whether Baltimore credits its $75 application fee (Howard is $20 lower if not, Baltimore County $55 lower if so), while Baltimore County wins on larger ones under either assumption (about $270 vs $160 to $235 at 800 sq ft) and the gap grows from there. Two cautions apply. First, Baltimore County's schedule does not say whether the $75 application fee is credited toward the permit; PermitPrice will update these figures once the county confirms, and you can ask the Department of Permits, Approvals and Inspections at 410-887-3900. Second, new construction is genuinely not comparable: Howard's $0.25/sq ft yields a clean number, but Baltimore County only publishes a Category D $280 minimum without a residential per-square-foot rate, so we do not put a Baltimore new-home total head-to-head. Howard County's schedule (410-313-2455) is current as of July 1, 2026.

Frequently Asked Questions

It depends on size and on Baltimore County's $75 application fee. A 400 sq ft addition is about $160 in Howard County vs $105 to $180 in Baltimore County ($105, or $180 if the $75 application fee is not credited toward the permit), so either county can be lower; an 800 sq ft addition is about $270 in Howard vs $160 to $235 in Baltimore County, so Baltimore County is $35 to $110 lower. Baltimore County charges flat fees by size band plus a separately listed $75 application fee, while Howard charges $0.25 per square foot plus a $50 filing fee and a 10% technology fee.
Howard County prices a new house at $0.25 per square foot, which gives a clear number (about $810 for a 2,400 sq ft house). Baltimore County's fee schedule lists residential new construction under Fee Category D with a $280 minimum but does not publish a per-square-foot rate that applies above the minimum, so we cannot compute a comparable Baltimore new-home total. We do not publish a single Baltimore new-home figure to avoid implying a number the schedule does not state.
Howard adds a 10% technology fee on the permit fee; Baltimore County does not add a technology fee but lists a separate $75 residential application fee. Neither county adds a statewide Maryland levy - Maryland has no equivalent of Virginia's 2% USBC levy. The $50 Maryland Home Builder Guaranty Fund fee applies to new-home permits in both counties.
Baltimore County's current building permit fee schedule took effect July 1, 2026 (PAI BPP 15 Attachment A, Rev 6/30/26) and replaced the 2018 schedule. PermitPrice re-verified it on November 4, 2026. Baltimore County's schedule lists a separate $75 residential permit application fee and does not say whether it is credited toward the permit fee, so PermitPrice shows Baltimore totals with and without it and will update them once the county confirms.
Howard County's fee schedule is current, effective July 1, 2026 (FY2027). Baltimore County's schedule is also current, effective July 1, 2026. See the Howard County and Baltimore County pages for full detail.

Sources

Official Sources
Next Step

See each county's full fee page, or compare more Maryland jurisdictions.

Verify current fees with each county before budgeting or filing. Howard County DILP: 410-313-2455. Baltimore County PAI: 410-887-3900.
Disclaimer: All fee information on PermitPrice is informational only and not an official permit quotation. Actual fees are determined by each county at the time of application. Baltimore County's $75 residential application fee is shown both with and without because its schedule does not say whether it is credited; its residential new-construction per-square-foot rate is unpublished, so no Baltimore new-home total is shown. Impact, excise, and school facility charges and trade permits are excluded from the figures on this page.

Written by: Munib Ur Rehman

Data verified against official fee schedule documents.